Packaging Corporation of America Sheet Plant

Project Type: Plan & Spec/Design Build
Location: Salt Lake City, Utah
Facility Size: 180,000 square feet
Project Duration: 16 months

Scope of Work:
Ground up construction, including design build services and specialty piping for equipment.

True Tech’s Role:
Assisted with the design build process, providing plumbing and specialty piping solutions to support the project’s equipment and operational requirements.

TrueCore

Project Type: Plan & Spec/Design Build
Location: Brigham City, Utah
Facility Size: 133,000 square feet
Project Duration: 12 months

Scope of Work:
Ground up construction, including specialty piping for equipment.

True Tech’s Role:
Worked directly with ownership to design and build an efficient piping system. The looped design helped maximize airflow and provide more consistent volume throughout the facility.

SKF Polyseal Inc

Project Type: Design Build
Location: West Valley City, Utah
Facility Size: 237,000 square feet

Project Duration: 6 months

Scope of Work:
Replacement of the facility’s process cooling piping, including thousands of feet of extra-heavy-duty PVC piping.

True Tech’s Role:
Coordinated and executed production sensitive work during nights and weekends to minimize disruption to facility operations and keep the project on schedule.

Hill Air Force Base Little Mountain Fire Station

Project Type: Ground Up Construction / Plan & Spec
Location: West Ogden, Utah
Facility Size: 6,000 square feet
Project Duration: 30 months

Scope of Work:
Complete plumbing scope for a new ground up fire station.

True Tech’s Role:
Coordinated closely with the general contractor to complete the plumbing scope while maintaining project schedules and construction requirements.

Wallace F. Bennett Building

Project Type: Design Build
Location: Salt Lake City, Utah
Facility Size: 14 story building/45,000 square feet
Project Duration: 6 weeks

Scope of Work:
Removal and replacement of the building’s culinary water lines.

True Tech’s Role:
Coordinated the replacement of the building’s water lines, working with multiple subcontractors to complete the project efficiently within a six-week schedule.

Rise Bakery

Project Type: Wastewater Treatment Upgrades
Location: Pleasant View, Utah
Facility Size: 126,000 square feet
Project Duration: 4 months

Scope of Work:
Designed and replaced existing wastewater pumps and associated underground piping, along with a complete interior plumbing remodel.

True Tech’s Role:
Coordinated with multiple subcontractors and project teams to complete the work within the required timeline while allowing the facility to maintain continuous production.

Kiln Remodel at The Gateway

Project Type: Plan & Spec
Location: Salt Lake City, Utah
Facility Size: 2 story building/54,000 square feet
Project Duration: 8 months

Scope of Work:
Complete interior plumbing scope for a major facility remodel.

True Tech’s Role:
Coordinated closely with the general contractor and other trades to complete the plumbing scope and support the overall project schedule.

Zion Bank Headquarters

Project Type: Ground water retention and pump system
Location: Midvale, Utah
Facility Size: 6 story/400,000 square feet
Project Duration: 2 weeks

Scope of Work: Project required advanced preparation and coordination with engineering and EPA. Project consisted of placing two vaults to accommodate ground water retention and ejection.
True Tech’s Role: Operated as the general contractor, coordinating with several subcontractors.